The New Humber River Hospital
Here's a view of the site from November 3, 2014
This is the Post-anesthesia Care Unit.
On the fourth level is our Maternal and Child program. This is one of the nurseries.
Level 5 is our Mental Health floor. Here is the paediatric outpatient mental health registration area.
Here is a group therapy room with a great view of the city and the 401.
This is a Critical Care room. Each of these rooms provides space for a family member to stay for an extended period of time.
This is a nursing substation under construction.
Level 14 is our Inpatient Rehabilitation Unit.
Here is the Occupational Therapy room.
The official groundbreaking ceremony took place on December 2, 2011.
Excavation continued throughout January The site was being prepared for pouring the concrete raft slab.
In April the second ralt slab pour took place. During the eight hour pour, 100 construction workers dispersed over three thousand cubic metres of concrete.
By May, work on the third floor of the Patient Tower is under construction
In June, the foundation of the South Podium was being built.
By August, the third floor of the Patient Tower was already under construction and there was progress on the Podiums
In October, interior work began in the lower levels of the hospital.
Here is the North Podium as seen from the ground in November This will be the main entrance to the hospital off of Wilson Ave.
Meanwhile, inside wallboard, electrical cable and duct work continued to be installed
Despite the cold, construction and concrete pour continued. Here is a concrete pour on the North Podium